Article 830
Section Three: Employment Contracts > Chapter One: Muqawala Contract > Part Two: Effects of Muqawala ContractFirst: Obligations of the Contractor
English translation
If the remuneration for the work is not specified in the contract, the contractor shall be entitled to the remuneration of the like, together with the value of the materials they have supplied as required by the work.
Official translation, as published by the portal.
Official Arabic text
إذا لم يعيّن في العقد أجر على العمل استحق المقاول أجر المثل مع قيمة ما قدّمه من المواد التي تطلبها العمل.
What it means when you sign
This article answers what happens when a contract for work does not state the price for the work. In that case the contractor is entitled to the remuneration normally paid for work of the same kind, together with the value of the materials the contractor supplied as the work required.
It does not say who sets that usual remuneration or how it is worked out. It only states the two parts of what the contractor can claim: a fair rate for the work itself, and the value of the materials supplied for it.
When you are about to sign, this article means a works contract that leaves the price blank, or refers to it without a figure, does not leave the contractor unpaid. The payment falls back on the usual rate plus materials. A clause that states a price, a payment schedule or a price for materials may take the place of this default, so the pricing clause is the one to read closely. If the contract is silent on whether materials are included in the price, this article is the rule that deals with that gap for materials the work required.
Not yet cited in a Fahm report; shown because it sits in the same chapter as one that is.
Related articles
- Article 817In a muqawala contract, where a contractor carries out work for an employer, this article says who supplies the additional machinery and tools needed to finish the work.
- Article 818Cited in Fahm reportsThis article sets out how the contractor must carry out the work and what the employer may do if it goes wrong.
- Article 819The contractor is liable for any damage or loss that results from their own act or workmanship, whether it arises from their transgression or negligence or from some other cause.
- Article 828This article deals with a contract priced on a bill of quantities (BOQ) at unit prices, where the work turns out to need more than was estimated.
- Article 829Cited in Fahm reportsThis article covers a contractor who agrees to do work from an agreed design for a lump-sum price.
- Article 18This article says which country's law governs property.